| Project Company | EPR Eye Limited |
|---|---|
| Capacity | 12.7MW |
| Fuel | Poultry Litter, Horse bedding 12% and Feathers 7% (160 kt/yr) |
| Technology Employed | Conventional moving grate boiler and steam cycle |
| Date of Commission | July 1992 |
| Ownership | 100% EPR |
| Plant Procurement | Built under a turnkey contract by Aalborg Boilers A/S. Turbine provided by NEI-Allen (W.H Allen of Bedford). Foster Wheeler Energy Ltd acted as Owner's Engineer. |
| Operation and Maintenance | Directly employed management and staff |