| Project Company | EPR Glanford Limited |
|---|---|
| Capacity | 13.5MW |
| Fuel | MBM from May 2000. Can re-commission to combust poultry litter |
| Technology Employed | Conventional moving grate boiler and steam cycle |
| Date of Commission | November 1993 |
| Ownership | 100% EPR |
| Plant Procurement | Boiler supplied by Aalborg Boilers A/S. Turbine provided by NEI-Allen (W.H. Allen of Bedford). Foster Wheeler Energy Ltd acted as Owners' Engineer on the project |
| Operation and Maintenance | Directly employed management and staff |